Our offshore experience

From wind farms to offshore platforms and subsea connections, our projects span the Middle East, Europe and Asia.

Projects delivered
10K+
Homes powered
2.5M
Offshore wind enabled
4,000+MW
Mattresses delivered
55K+
Grout bags delivered
200K+

Major projects

A selection of ULO’s major projects. Open a row for the full scope, the figures and, where ULO recorded one, how long it took.

Offshore wind

Grouting for wind turbine foundations and offshore substations.

4
  • Fengmiao 1 offshore wind farmTaiwan · Peak Wind · EPCI CDWE33 jackets
    Scope
    Pile grouting for 33 jacket foundations and one offshore substation.
    Delivered
    33jacket foundations1offshore substation
    Timeline
    2026
  • Hai Long offshore wind farmTaiwan · Northland Power · Mitsui · Gentari · EPCI CDWE73 foundations
    Scope
    Grouted connections for 73 jacket-foundation turbines in the Taiwan Strait.
    Delivered
    73turbine foundations1,022MWcapacity2offshore substations
    Timeline
    2024–2025
  • Zhong Neng offshore wind farmTaiwan · CIP · China Steel (CSC) · EPCI CDWE31 turbines
    Scope
    Grouted connections across 31 turbine foundations.
    Delivered
    31turbines300MWcapacity
    Timeline
    2023
  • Changfang & Xidao (CFXD)Taiwan · CIP · COP · EPCI CDWE52 turbines
    Scope
    Grouted connections across 52 turbine foundations.
    Project details
    Pre-piled turbine jacket foundations with more than 150 legs and piles across multiple three-legged foundations, all grouted inside a single 104-day window.
    Delivered
    52turbines600MWcapacity
    Timeline
    104 days · Q2–Q3 2023